Lorne Hotel, Glasgow

Glasgow city centre M&E fit out for student accommodation, 150 + rooms to be completed.  Mechanical aspects include ductwork and water services within apartments.

Electrical install within flats and main services to the building. Contract length 52 weeks.

Split into two feature buildings known as the 1960’s and the listed with the building containing 5 floors, each building has its own service riser and the co-ordination with all trades has been critical so achieving a high standard/quality of work.

Main contractor is PLG (park lane group). Various subcontractors working directly for BPS , these include lighting protection, insulators for pipework and air conditioning.

The completion date for this is the end of July with a view of opening this year for students starting university in the new term.